Checklist Template for Raft Foundation Work
CHECKLIST FOR RAFT FOUNDATION |
||||
Work Item |
yes |
No |
N/A |
Date |
1.0
Formworks. |
|
|
|
|
1.1 Formwork system approved. |
|
|
|
|
1.2 Method
statement for installation formwork approved. |
|
|
|
|
1.3 Setting
out, alignment, elevation, and dimension as per approved shop drawings. |
|
|
|
|
1.4 Formwork
surface must be cleaned and nails, residual concrete, etc. have been removed. |
|
|
|
|
1.5 Check
existing concrete is clean and ready to receive new concrete. |
|
|
|
|
2.0
Reinforcement. |
|
|
|
|
2.1
Reinforcement shop drawings approved. |
|
|
|
|
2.2
Reinforcement material submittal approved. |
|
|
|
|
2.3
Reinforcement tests reviewed and approved. |
|
|
|
|
2.4
Reinforcement method statement approved. |
|
|
|
|
2.5 Check
bottom/ top steel reinforcement distribution, diameter, splicing, and must be
free from rust. |
|
|
|
|
2.6 Check all
embedded items and concrete cover are in place as per approved shop drawings. |
|
|
|
|
2.7 Check
starter bars are in place as per approved drawings. |
|
|
|
|
2.8 Check
construction joint are prepared as per approved drawings. |
|
|
|
|
2.9 Check
additional reinforcement around opening. |
|
|
|
|
3.0 Pre-Pour
Check |
|
|
|
|
3.1 Concrete
levels are marked by surveyors at regular intervals. |
|
|
|
|
3.2 Ensure
that all areas to be cast are clean and free from debris, left over building binding
wires, etc. |
|
|
|
|
3.3 Ensure
the sufficient equipment are available in site even the spare in case of
emergency. |
|
|
|
|
3.4 Provide sufficient
light during night casting. |
|
|
|
|
3.5 Ensure
that concrete design mix approved from Engineer. |
|
|
|
|
3.6 Ensure
that all MEP work completed and approved from Engineer. |
|
|
|
|
4.0 During
Pouring. |
|
|
|
|
4.1 Check concrete
delivery as per approved concrete design mix. |
|
|
|
|
4.2 Check the
required concrete test (slump, concrete temperature) as per project
specification |
|
|
|
|
4.3 Take the
required number of concrete cubes or cylinder for the required concrete tests
as per project specification. |
|
|
|
|
4.4 Check
that all concrete finishes is as per specification and drawings. |
|
|
|
|
4.5 Cold
joint must be avoided by proper sequence of pour. |
|
|
|
|
4.6 Check for
the type of curing to be done. |
|
|
|
|