Checklist Template for Raft Foundation Work
Loading ... Civil Engineers Blog

top page

Latest News

top post page

Home Checklist Template for Raft Foundation Work

Checklist Template for Raft Foundation Work

Font size





Checklist Template for Raft Foundation Work


Checklist help inspector to identify the items and steps to be checked during inspection request. Checklist not have standard format we can use any format but it should include all processes steps and documents which should be checked during inspection.

In this article, we will show checklist for raft foundation work.

CHECKLIST FOR RAFT FOUNDATION

Work Item

yes

No

N/A

Date

1.0 Formworks.

 

 

 

 

1.1   Formwork system approved.

 

 

 

 

1.2 Method statement for installation formwork approved.

 

 

 

 

1.3 Setting out, alignment, elevation, and dimension as per approved shop drawings.

 

 

 

 

1.4 Formwork surface must be cleaned and nails, residual concrete, etc. have been removed.

 

 

 

 

1.5 Check existing concrete is clean and ready to receive new concrete.

 

 

 

 

2.0 Reinforcement.

 

 

 

 

2.1 Reinforcement shop drawings approved.

 

 

 

 

2.2 Reinforcement material submittal approved.

 

 

 

 

2.3 Reinforcement tests reviewed and approved.

 

 

 

 

2.4 Reinforcement method statement approved.

 

 

 

 

2.5 Check bottom/ top steel reinforcement distribution, diameter, splicing, and must be free from rust.

 

 

 

 

2.6 Check all embedded items and concrete cover are in place as per approved shop drawings.

 

 

 

 

2.7 Check starter bars are in place as per approved drawings.

 

 

 

 

2.8 Check construction joint are prepared as per approved drawings.

 

 

 

 

2.9 Check additional reinforcement around opening.

 

 

 

 

3.0 Pre-Pour Check

 

 

 

 

3.1 Concrete levels are marked by surveyors at regular intervals.

 

 

 

 

3.2 Ensure that all areas to be cast are clean and free from debris, left over building binding wires, etc.

 

 

 

 

3.3 Ensure the sufficient equipment are available in site even the spare in case of emergency.

 

 

 

 

3.4 Provide sufficient light during night casting.

 

 

 

 

3.5 Ensure that concrete design mix approved from Engineer.

 

 

 

 

3.6 Ensure that all MEP work completed and approved from Engineer.

 

 

 

 

4.0 During Pouring.

 

 

 

 

4.1 Check concrete delivery as per approved concrete design mix.

 

 

 

 

4.2 Check the required concrete test (slump, concrete temperature) as per project specification

 

 

 

 

4.3 Take the required number of concrete cubes or cylinder for the required concrete tests as per project specification.

 

 

 

 

4.4 Check that all concrete finishes is as per specification and drawings.

 

 

 

 

4.5 Cold joint must be avoided by proper sequence of pour.

 

 

 

 

4.6 Check for the type of curing to be done.

 

 

 

 