Backfilling Checklist Template
CHECKLIST FOR BACKFILLING |
||||
Work Item |
yes |
No |
N/A |
Date |
1.0 Material
Classification |
|
|
|
|
1.1 Material
submittal approval |
|
|
|
|
1.2 Material
test result reviewed and approved |
|
|
|
|
1.3 Method
statement approved |
|
|
|
|
2.0
Preparation prior backfilling. |
|
|
|
|
2.1 Backfilling material was clean free from debris, rubbish, etc. |
|
|
|
|
2.2 MEP
clearance approved. |
|
|
|
|
3.0
Backfilling process |
|
|
|
|
3.1
Approximate (200 mm per layer after compaction) complete the designed area
prior to start compaction |
|
|
|
|
3.2 Compact
the layer up to the required degree of compaction was attained. |
|
|
|
|
4.0 Field
density test (FDT) |
|
|
|
|
4.1 Every
layer conduct DFT |
|
|
|
|
4.2 To be
conducted by approved third party Laboratory. |
|
|
|
|
4.3 Proceed
to the next layer once the area reached the required degree of compaction |
|
|
|
|
5.0 MEP
Provision |
|
|
|
|
5.1
Coordinate with MEP for the location of MEP provision |
|
|
|
|
5.2 Setting
out and cutting can be apply as per the approved MEP drawings |
|
|
|
|
5.3 Concrete
protection for MEP services can be done if required |
|
|
|
|
5.4 Secure
the approval of MEP Engineer |
|
|
|
|
|
|
|
|
|