Form-work system- Golf Scaffolding System- part 2
In the previous articles (Form-work system-Golf Scaffolding System) we took the below from Golf scaffolding system:
- PS system/GC system/Cup-lock.
- Shorelok/Ring Lock system.
- SPF-50 system.
- Aluminum system / Perfect Aluminum Panels.
- Eco-form system.
- Table system.
In this article we will take:
- Soldier system
- waling system
- Supporting Frame System
- Special Form work System
- Access Scaffolding System
- Climbing Bracket
- Circular Form work System
Soldier System:
- The steel soldier form-work is designed to be applied to a wide range of construction applications and to withstand high fresh concrete pressure.
- The chief component for the steel soldier system is the steel beam, which is produced in various sizes of up to 360 cm. With its unrivaled strength-to-weight ratio.
- Versatility and range of accessories any forming application can be handled safely and easily.
- The steel soldiers are renowned for versatility and exceptional heavy-duty shoring capacity, the steel soldier are ideal for large slabs, bridge decks, tunnel forms and beams.
- In addition, the system provides an adaptable and economic form work system which can be used in a range of wall forming and slab support applications.
- The system combines high performance with simple, rapid assembly great versatility and major cost advantages.
- The steel soldier system provides maximum benefits when used with heavy duty ties and aluminum waling.
- Timber waling can also be used as another option at optimum spacing.
Waling System:
- The Waling form-work is one of the most adaptable form-work systems available. This form-work system combines H 20 timber beams with steel waling so perfectly.
- It adapts to all heights and widths, accommodates every pressure, and meets all construction demands.
- The basis of the Waling is the H 20 timber beam. It is produced in production plant with European standards.
- The H 20 beam is sturdy, easy to handle and offers a high load-bearing capacity at large distances of waling.
- The steel waling, clamped onto the H 20 timber beam, allow the form-work elements to be assembled quickly and simply.
- The assembly is done as easily as the disassembly.
- The Waling can be used for all vertical form-work applications, walls, columns and retaining walls form- work.
Supporting Frame System:
- The Supporting Frame is simply ideal for Single- Sided form-work applications.
- Regardless of whether single sided forming is to be used against existing building rows of bored piles, the concrete pressure and lifting forces must be discharged reliably into the ground.
- The Supporting Frame provides a safe and economical solution for these tasks.
Special Form-work System:
- Perfect Steel designs and produces the form-work equipment, scaffolding and other accessories required for the construction of bridges, culverts, and tunnels.
- The company offers innovative form-work solutions using its experience in activities in this industry for over a quarter of a century.
Access Scaffolding System:
- One of the key strengths of the heavy-duty access scaffold system is the simplicity of the component range, as well as the basic horizontals and verticals that form the core of all structures.
Climbing Bracket:
- The PS 200 climbing Bracket is widely used in the concrete pouring of pier, high-rise building, and varying structure.
- The concrete lateral pressure is entirely supported by anchor system and the wall-through tie-rods, additional reinforcement is not needed.
- The construction is easy, rapid, and economical, and the surface of the concrete is slick.
- The biggest advantage of PS 200 Climbing Bracket is safety and convenience in use.
Circular Form-work System:
- Circular column form-work provides contractors with safe, versatile, and economic circular steel forms.
- The key-bolt simply turns two identical steel half-shell structures into a perfect round structural form.