PMP Free Course- Tailoring and Lessons Learned
Loading ... Civil Engineers Blog

top page

Latest News

top post page

Home PMP Free Course- Tailoring and Lessons Learned

PMP Free Course- Tailoring and Lessons Learned

Font size


PMP Free Course- Tailoring and Lessons Learned

During this article we will see processes, practices, techniques, procedures, and rules for project management. However, that is not mean that is all practices written in this document should be applied in all projects.

When you are managing a project, depending on characteristics of a project you should select a process, tools, techniques, etc. required to manage a project.

For example, if you will not purchase any materials for your project, you might not need procurement processes in your project or some other processes in other knowledge areas might be not necessary for your project. So, you should not include those processes in your project management approach.


 - Tailoring.

Define as selecting appropriate tools, techniques, procedures, etc. to manage a project.

Tailoring can be done with a project team, sponsor, organization management and other related parties with project management in organization.

Tailoring is necessary because each project is unique. Not every processes, tools, or techniques will be required for every project. You must be aware of a tool, techniques, processes and should tailor your project accordingly based on required tools and techniques processes.


- Lessons learned.

We have seen in previous articles that is lessons learned documentation is very important organizational process assets of a company to consider when initiating a project. But why is important, what it is include, we will see it in this article.

- Lessons learned of a project includes:

- What was done right.

The best practices applied during a project recorded in a document by this way future projects get inspired from these best practices and have the benefit of these right implications.

- What was done wrong.

Wrong decisions or wrong procedures that causes project team to deliver slower outputs, it all documented and what could do to not face these problems all stored in lessons learned.

- What would be done better if the project could be re-done.

For example, if the project had problems to resources availabilities or planning weakness these should documented with reasons.


- Lessons learned should cover:

- Technical aspects of the project.

This include the schedule performance, cost performance and quality performance of a project.
For example, what was the planned budget and what is the completion budget, what was the planned schedule and what is the completion schedule. These kind of plans values and actual values must be included, and variance should be given inside of all over performance of a project.

- Project management plans.

Such as work breakdown structure (WBS) of a project, risk plan, schedule plan, cost plan, procurement plan, etc. and all management plans must be archived in the lessons learned documentation for future references.

- Management (communication, leadership).

Lessons learned documentations should also give recommendation on management communication and leadership.
For example, if there were a communications mistake, these should be mentioned and what could be done for better communications must be mentioned in documents.

The below figure give the role of lessons learned and how it was improved with a help of new projects in an organization.



Before starting a new project, organization process assets library of an organization is searched to check whether is any useful lessons learned hints that can help in the new project.
Then useful hints are used during the new project and new lessons learned are gathered throughout the project lifecycles. These new lessons learned are used in other current projects of the organization.
At the end of the project, lessons learned documentations is finalized and placed already on organizational process assets library of an organization in order to use in future projects.
















Labels:
No comments
Post a Comment